                        Questions on Project Time Management

                        PREVIOUS: Scope       UP NEXT: Risk

                        Questions

                        1. Activity Definition is typically performed by which of the following:
                          1. Project Manager who created the WBS
                          2. Project Team Members responsible for the work package
                          3. Project Officer
                          4. Project Stakeholder
                          CORRECT: Answer: B
                        2. Which of the following is not an activity attribute:
                          1. Person responsible for the activity
                          2. Location where to perform the activity
                          3. Time when to perform the activity
                          4. Leads and Lags
                          CORRECT: Answer: C Activity attributes are an input for project schedule development; therefore, the scheduling information is not a part of the activity attribute.
                        3. Which of the following does NOT generate changes to the Project documents:
                          1. Define Activities
                          2. Sequence Activities
                          3. Estimate Activity Resources
                          4. Estimate Activity Durations
                          CORRECT: Answer: A. Project document updates is an output to all processes in Project Time Management process area except Define Activities.
                        4. Which of the following may generate a milestone list:
                          1. Define Activities
                          2. Sequence Activities
                          3. Estimate Activity Resources
                          4. Estimate Activity Durations
                          CORRECT: Answer: A
                        5. In PDM, which of the following relationships is rarely used:
                          1. Finish-to-Start
                          2. Start-to-Finish
                          3. Start-to-Start
                          4. Finish-to-Finish
                          CORRECT: Answer: B
                        6. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
                          1. Finish-to-Start
                          2. Start-to-Finish
                          3. Start-to-Start
                          4. Finish-to-Finish
                          CORRECT: Answer: A
                        7. A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of:
                          1. ADM
                          2. PDM
                          3. A dependency with lag
                          4. A dependency with lead
                          CORRECT: Answer: D Note that this dependency can be represented by both ADM and PDM techniques.
                        8. The following BEST describes a subnetwork:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Fragment Network
                          4. Activity-On-Node [AON]
                          CORRECT: Answer: C
                        9. A Project Manager in-charge of a Software Development projects is creating a project schedule network diagram for the code development component of the project. This is an example of:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Fragment Network
                          4. Activity-On-Node [AON]
                          CORRECT: Answer: C It is not clear what Activity Sequencing technique is the Project Manager using; however, it is evident that she is developing a schedule network diagram for only part of the project (not the entire project)
                        10. What-if scenario analysis is done as a part of which process:
                          1. Sequence Activities
                          2. Define Activities
                          3. Develop Schedule
                          4. Control Schedule
                          CORRECT: Answer: C
                        11. AON refers to:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Fragment Network
                          4. Mandatory Dependencies
                          CORRECT: Answer: A
                        12. AOA refers to:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Fragment Network
                          4. Mandatory Dependencies
                          CORRECT: Answer: B
                        13. Activity Resource Requirements is an input to which of the following processes:
                          1. Estimate Activity Durations
                          2. Control Schedule
                          3. Estimate Activity Resources
                          4. Sequence Activities
                          CORRECT: Answer: A One of the outputs of Estimate activity resources is Activity Resource Requirements. Sequence Activities establishes logical dependencies between activities. Activity Resource requirements do not play an important role in determining the seq
                        14. Dummy relationships or dummy activities can be used in which of the following Activity Sequencing techniques:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Fragment Network
                          4. Schedule Network Templates
                          CORRECT: Answer: B
                        15. Which of the following is NOT an input to the Sequence Activities process:
                          1. Project Scope Statement
                          2. Activity Attributes
                          3. Activity List
                          4. Change Requests
                          CORRECT: Answer: D Approved Change Requests is not a valid input to Sequence Activities process.
                        16. Which of the following is a technique for Sequence Activities:
                          1. Precedence Diagramming Method [PDM]
                          2. Arrow Diagramming Method [ADM]
                          3. Rolling Wave Planning
                          4. Mandatory Dependencies
                          CORRECT: Answer: A
                        17. Reserve Analysis is a technique for:
                          1. Define Schedule
                          2. Sequence Activities
                          3. Estimate Activity Resources
                          4. Estimate Activity Durations
                          CORRECT: Answer: D
                        18. Resource Leveling is a technique for:
                          1. Develop Schedule
                          2. Sequence Activities
                          3. Estimate Activity Resources
                          4. Estimate Activity Durations
                          CORRECT: Answer: A
                        19. Following can be BEST described as a kind of dependency that can create arbitrary float values and limit scheduling options:
                          1. Mandatory dependency
                          2. Discretionary dependency
                          3. Start-to-Finish dependency
                          4. External dependency
                          CORRECT: Answer: B
                        20. Critical path method is used in which of the following processes:
                          1. Sequence Activities
                          2. Define Activities
                          3. Develop Schedule
                          4. Estimate Activity Durations
                          CORRECT: Answer: C
                        21. Parametric Estimating is done as a part of which process:
                          1. Sequence Activities
                          2. Develop Schedule
                          3. Estimate Activity Resources
                          4. Estimate Activity Durations
                          CORRECT: Answer: D
                        22. Identification of Mandatory Dependencies is BEST done during which process:
                          1. Sequence Activities
                          2. Develop Schedule
                          3. Define Activities
                          4. Estimate Activity Duration
                          CORRECT: Answer: A
                        23. Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique:
                          1. Critical Path Method
                          2. Schedule Compression
                          3. What-if Analysis
                          4. Resource Leveling
                          CORRECT: Answer: D
                        24. Knowledge of best practices in a particular area is MOST likely to give rise to which of the following dependencies:
                          1. Finish-to-Start dependency
                          2. Soft Logic
                          3. Mandatory dependency
                          4. External dependency
                          CORRECT: Answer: B Discretionary dependencies often result from best practices. This kind of dependency is also known as Soft Logic, Preferential Logic, or Preferred Logic.
                        25. A Project Manager is preparing a Project Schedule network diagram. During the diagram development, she removes a dependency between two tasks that was defined in an earlier stage. After the network diagram is completed, she updates activity attributes for the two tasks. This is an example of:
                          1. Define Activities
                          2. Sequence Activities
                          3. Develop Schedule
                          4. Lack of change control
                          CORRECT: Answer: D The Project manager is preparing the project schedule network diagram which implies she is in the Activity scheduling process. This process can generate changes to the Activity definition and Activity Attributes; however, such changes should
                        26. Reserve Analysis involves:
                          1. Estimating by multiplying the quantity of work by productivity rate
                          2. Incorporating time buffers into the activity duration estimates
                          3. Developing project schedule with contingency reserves as a recognition of the schedule risk
                          4. Adding resource reserves to the activity resource estimates
                          CORRECT: Answer: B Answer C might seem more likely, but note the fine difference that Reserve Analysis is purely a technique of determining activity duration, not a schedule development technique.
                        27. Which of the following is not true for Resource Leveling:
                          1. Project schedule is build with resource buffers to prevent schedule slippage
                          2. Project’s Critical path may be altered
                          3. Resource based scheduling method
                          4. Reverse resource allocation scheduling
                          CORRECT: Answer: A Resource leveling involves creating a resource constrained project schedule.
                        You have answered  of 27 questions correctly.

                        More Options

                        Visit the Time tutorial to brush up the topic.

                        UP NEXT: Risk

                        Upcoming Classes

                        Jun 4
                        Dallas - 1 Day Boot Camp

                        12400 Coit Road
                        PreparePM Training Center
                        Dallas, TX 75251
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 9
                        Denver - 1 Day Boot Camp

                        10004 Park Meadows
                        PreparePM Training Center
                        Centennial, CO. 80124
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 9
                        Phoenix - 1 Day Boot Camp

                        4615 East Elwood Street
                        PreparePM Trainin Center
                        Phoenix, AZ. 85040
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 10
                        Atlanta - 1 Day Boot Camp

                        859 Mount Vernon Parkway
                        Preparepm Training Center
                        Atlanta, GA 30328
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 15
                        Chicago - 1 Day Boot Camp

                        203 North LaSalle
                        PreparePM Training Center
                        Chicago, IL. 60601
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 15
                        San Francisco - 1 Day Boot Camp

                        One Front Street
                        PreparePM Training Center
                        San Francisco, CA. 94111
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 17
                        Baltimore - 1 Day Boot Camp

                        8830 Stanford Blvd.
                        PreparePM Training Center
                        Columbia, MD. 21045
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 17
                        Houston - 1 Day Boot Camp

                        11451 Katy Freeway
                        PreparePM Training Center
                        Houston, TX 77079
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 18
                        Minneapolis - 1 Day Boot Camp

                        435 Ford Road
                        PreparePM Training Center
                        Minneapolis, MN. 55426
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 19
                        Raleigh - 1 Day Boot Camp

                        4 Copley Parkway
                        PreparePM Training Center Morrisville, NC 27560
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 24
                        Orlando - 1 Day Boot Camp

                        8325 South Park Circle
                        PreparePM Training Center
                        Orlando, FL. 32819
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 29
                        Detroit - 1 Day Boot Camp

                        26261 Evergreen Road
                        PreparePM Training Center
                        Southfield, MI. 48076
                        8:00 AM-6:00 PM

                        Purchase

                        Jun 30
                        Houston - 1 Day Boot Camp

                        11451 Katy Freeway
                        PreparePM Training Center
                        Houston, TX 77079
                        8:00 AM-6:00 PM

                        Purchase

                        Jul 1
                        New York - 1 Day Boot Camp

                        63 West 35th Street
                        PreparePM Training Center
                        New York, NY. 10001
                        8:00 AM-6:00 PM

                        Purchase

                        Jul 6
                        Seattle - 1 Day Boot Camp

                        1700 7th Avenue
                        PreparePM Training Center
                        Seattle, WA. 98101
                        8:00 AM-6:00 PM

                        Purchase

                        For more dates and locations, please visit our individual city pages, or call our office to speak with a PreparePM representative.

                        Testimonials

                        • I took the boot camp last Monday thru Thursday and I passed my PMP, on my first attempt, on Friday afternoon.

                          Lorna Lavelle, PMP
                        • I took my bootcamp last week and passed the next day. My instructor was easily one of the best instructors I've ever had.

                          Timothy Hopkins, PMP
                        • I leveraged the course as somewhat of a capstone to my preparation period. I took the exam the very next day after the boot camp ended, and passed.

                          Acie Slade PMP

                                              aviation

                                              Buy a car

                                              entertainment

                                              video

                                              image

                                              Information

                                              aviation

                                              Super League

                                              aviation